Operations strategy

Business A2 · Operations management. The idea in plain words, the rules to remember, the mistake to avoid and a worked example, written and checked by Mega Lecture.

Test this topic freeAll Business A2 topics

The idea

Operations decisions depend on the resources a business has: the skills of its workers, the finance available and the demand forecast from marketing. IT and AI now help with forecasting, scheduling and maintenance. Operations must also be flexible in volume, delivery time and specification.

Enterprise resource planning (ERP) is one software system with one database that links all departments, so everyone uses the same up-to-date information. Lean production aims to cut every kind of waste while keeping quality high.

Large projects are planned with a network diagram. Critical path analysis finds the longest path through the network. That path gives the minimum project duration, and its activities cannot be delayed.

In simpler words

Operations is about how a firm makes its products. Lean production tries to cut all waste, like spare stock or wasted time. ERP is one computer system that links every department. Big projects are planned with a network diagram. The critical path is the longest route through the diagram. It shows the shortest time the whole project can take.

An everyday comparison

The critical path is like getting ready for school. You can eat breakfast while the iron heats up, but you cannot leave until you are dressed, fed and packed. The longest chain of jobs that must happen in order decides when you leave. The comparison stops working because a real project has costs and resources to share between tasks, not just time.

Rules to remember

Common mistake

Students choose the shortest path as the critical path. The critical path is the longest path, because every activity must be finished before the project is complete.

In the exam

Draw the network carefully, then work out earliest start times forwards and latest finish times backwards. Identify the critical path as the longest path and state the minimum project duration. For float, write total float = latest finish − duration − earliest start, then substitute. Show that critical activities have zero float. Explain what happens if a critical activity is delayed. For lean production, JIT or kaizen, give one benefit and one risk for the firm in the case.

Worked example

A project has activities A (3 days), B (6 days), C (4 days, after A), D (5 days, after B), E (2 days, after C) and F (4 days, after D and E). Find the minimum duration, the critical path and the total float of C.

  1. Path A → C → E → F = 3 + 4 + 2 + 4 = 13 days. Path B → D → F = 6 + 5 + 4 = 15 days.
  2. The longest path is B → D → F, so the minimum duration is 15 days and F cannot start before day 11 (6 + 5).
  3. E must finish by day 11, so C must finish by day 11 − 2 = day 9. C can start at day 3.
  4. Total float of C = latest finish − duration − earliest start = 9 − 4 − 3 = 2 days.

Answer: Minimum duration 15 days; critical path B → D → F; total float of C = 2 days.

Ask about this

Type what you are stuck on. The helper finds the explanation, worked examples and the notes to read, free and instant.

Read the full notes