The idea

A standard cost is the planned cost of one unit: how much material and labour it should use and what each should cost. At the end of the period actual results are compared with the standard for the actual output. Each difference is a variance.

A variance is favourable if it makes profit higher than planned and adverse if it makes profit lower. Each total variance is split in two: one part for the price paid and one part for the quantity used. This shows managers where to look and who is responsible.

Variances are often linked. Cheaper material may give a favourable price variance but more waste, so an adverse usage variance.

In simpler words

A standard cost is the planned cost of making one unit. After the period, the business compares what really happened with that plan for the real output. The difference is called a variance. If it raises profit, it is favourable. If it lowers profit, it is adverse. Each variance is split into a price part and a quantity part to show who is responsible.

An everyday comparison

A standard cost is like a recipe that says a cake needs 200 g of flour at a set price. If you pay more for flour, that is a price variance; if you spill some and use more, that is a usage variance. The comparison stops because a business measures the standard for its actual output, not for one cake.

Rules to remember

Common mistake

Students compare actual usage or hours with the standard for the budgeted output. Always use the standard quantity or hours for the actual output.

In the exam

For each variance, write the formula first, then substitute, then give the amount and label it F or A. Use the standard quantity or hours for the actual output, never the budgeted output. Show price before usage, rate before efficiency. Check that the parts add to the total variance. Then explain possible causes and links, for example cheaper material giving a favourable price variance but an adverse usage variance.

Worked example

The standard for one unit is 2 labour hours at $12 per hour. Actual output was 1500 units. The workers took 3150 hours and were paid $36 225. Calculate the labour rate and efficiency variances.

  1. Rate variance = (3150 hours × $12) − $36 225 = $37 800 − $36 225 = $1575 favourable.
  2. Standard hours for actual output = 1500 × 2 = 3000 hours.
  3. Efficiency variance = (3000 − 3150) × $12 = −$1800, so $1800 adverse.
  4. Check: standard cost 3000 × $12 = $36 000; actual $36 225; total $225 adverse = $1575 F − $1800 A.

Answer: Labour rate variance $1575 favourable; labour efficiency variance $1800 adverse.

Ask about this

Type what you are stuck on. The helper finds the explanation, worked examples and the notes to read, free and instant.

Read the full notes

Keep going

← Activity based costing (ABC)Budgeting and budgetary control →Take a Accounting A2 test